... practical failures through the large amount of ground water leaking into the system , and the importance of this subject of joint - making can hardly be over- estimated . In order to prevent leakage , many special forms of joints have ...
... practical failures through the large amount of ground water leaking into the system , and the importance of this subject of joint - making can hardly be over- estimated . In order to prevent leakage , many special forms of joints have ...
Página 35
... practical purposes may therefore be taken as equal to the same . To compare the amount of brickwork in circular sewers and in egg - shaped sewers , Folwell says that the diameter of a circular sewer having an equal area with an egg ...
... practical purposes may therefore be taken as equal to the same . To compare the amount of brickwork in circular sewers and in egg - shaped sewers , Folwell says that the diameter of a circular sewer having an equal area with an egg ...
Página 104
... practical foundry- man before their formal adoption . To facilitate molding , the stiffening ribs should not be so deep or so close together that the sand clings and breaks off from the rest of the mold , as will be the case unless the ...
... practical foundry- man before their formal adoption . To facilitate molding , the stiffening ribs should not be so deep or so close together that the sand clings and breaks off from the rest of the mold , as will be the case unless the ...
Página 161
... practical value , since the screen is placed below the precipitation tank beyond which few solids passed . A unique form of mesh screen was used at the Cranston , R.I. , outlet ( see Fig . 131 ) , where the wire mesh was made up in the ...
... practical value , since the screen is placed below the precipitation tank beyond which few solids passed . A unique form of mesh screen was used at the Cranston , R.I. , outlet ( see Fig . 131 ) , where the wire mesh was made up in the ...
Página 172
... practical application . The construction illustrated was built in Milwaukee , where it was necessary to divert the dry - weather sewage flow of some twelve old outlet sewers from the Menom- inee River into the new intercepting sewer ...
... practical application . The construction illustrated was built in Milwaukee , where it was necessary to divert the dry - weather sewage flow of some twelve old outlet sewers from the Menom- inee River into the new intercepting sewer ...
Otras ediciones - Ver todas
Términos y frases comunes
12 inches 50 cents 8-inch pipe amount arch basin blocks Board bottom brick sewer brickwork built cast cast-iron Catch-basin cement clause clay cleaning concrete sewer construction contract Contractor cost crete cubic yard Cyanide Process depth Descriptive Geometry drain drilling earth Electrolysis engineer Engineering-Contracting estimate excavation feet deep feet wide filling flow furnish grade gravel ground holes horizontal inches inches thick inlet invert Inverted siphon iron joint labor laid Large 12mo length lineal foot load Machine main sewer manhole Manual masonry material Mechanics molded Moore Machine mortar necessary outfall outlet overflow piles plank pounds pumping Qualitative Chemical Analysis refilling reinforced reinforced concrete rock rods sand screen chamber sewage sewer pipe sheeting shown in Fig shows side siphon specifications steel stone street Strength of Materials surface tion trap Treatise trench vertical vitrified walls width
Pasajes populares
Página 337 - Kemp and Waugh's Landscape Gardening. (New Edition, Rewritten. In Preparation.) * McKay and Larsen's Principles and Practice of Butter.making...
Página 338 - I2mo, 3 oo Eissler's Modern High Explosives 8vo, 4 oo * Fiebeger's Text-book on Field Fortification Small 8vo, 2 oo Hamilton's The Gunner's Catechism i8mo, I oo * Hoff's Elementary Naval Tactics 8vo, i 50 Ingalls's Handbook of Problems in Direct Fire 8vo, 4 oo * Ballistic Tables 8vo.
Página 282 - Contractor, and in case any question shall arise between the parties hereto, touching this contract, such estimate and decision shall be a condition precedent to the right of the Contractor to receive any money under this contract.