Página 42
... deduction shall be made . No allow- ance will be made for anticipated profits . 30. Inconsistencies and Omissions . ( a ) Many cases involving inconsistencies between plans and specifications have found their way to the courts . A recog ...
... deduction shall be made . No allow- ance will be made for anticipated profits . 30. Inconsistencies and Omissions . ( a ) Many cases involving inconsistencies between plans and specifications have found their way to the courts . A recog ...
Página 50
... Contractor to do any particular work or to furnish any particular materials , or as to the reasonable value of any additional work or materials required by the Engineer , or as to the deduction 50 THE ELEMENTS OF SPECIFICATION WRITING.
... Contractor to do any particular work or to furnish any particular materials , or as to the reasonable value of any additional work or materials required by the Engineer , or as to the deduction 50 THE ELEMENTS OF SPECIFICATION WRITING.
Página 51
... deduction to be made from the contract price for the construction of the ... by reason of any work or materials ... deduction from the amount payable to the Contractor on account of any reduction in the amount of work to be done which ...
... deduction to be made from the contract price for the construction of the ... by reason of any work or materials ... deduction from the amount payable to the Contractor on account of any reduction in the amount of work to be done which ...
Página 53
... the Engineer , the condemned material may be removed by ( the Owner ) and the cost of said removal deducted from any money that is then due or that may thereafter become due THE ENGINEER DURING CONSTRUCTION 53 Rejected Material.
... the Engineer , the condemned material may be removed by ( the Owner ) and the cost of said removal deducted from any money that is then due or that may thereafter become due THE ENGINEER DURING CONSTRUCTION 53 Rejected Material.
Página 79
... part ( the Contractor ) hereby further agrees that the said parties of the first part ( the Bridge Commissioners ) shall be and they are hereby authorized to deduct and retain out of all the moneys PROGRESS OF WORK 79.
... part ( the Contractor ) hereby further agrees that the said parties of the first part ( the Bridge Commissioners ) shall be and they are hereby authorized to deduct and retain out of all the moneys PROGRESS OF WORK 79.
Contenido
12 | |
15 | |
16 | |
17 | |
18 | |
19 | |
20 | |
21 | |
22 | |
27 | |
28 | |
29 | |
30 | |
31 | |
32 | |
35 | |
36 | |
38 | |
47 | |
52 | |
53 | |
54 | |
55 | |
56 | |
69 | |
70 | |
71 | |
73 | |
75 | |
77 | |
82 | |
87 | |
101 | |
104 | |
105 | |
106 | |
108 | |
109 | |
111 | |
112 | |
113 | |
114 | |
118 | |
122 | |
123 | |
124 | |
125 | |
Otras ediciones - Ver todas
Términos y frases comunes
00 Small 8vo Advertisement aforesaid agreed agreement amount Analysis arbitration bids bond bridge building Catskill Aqueduct cement cent certificate certified check Chapter Chemistry City Civil Engineers claim completion concrete construction contract Contractor cost courts cubic yard Deduct delay Electrolysis employees Engineer's Engineering Record estimate excavation expense extra finished furnished grades hardpan hereby Kensico Dam Khammurabi labor liquidated damages lump sum macadam Manhattan bridge Manual Manufacturers masonry material Mechanics ment method Municipal Engineering necessary otherwise Owner paid parties patent pavements paving payment penalty percentage performance person pipe plans and specifications plowing test practice Preparation proper proposal railroad reason Reference Riprap rock sewer sometimes specific clauses specifica steel stipulated stone Strength of Materials structure student sublet surety surety bond thereof tions tract tractor unit prices Water Williamsburg Bridge wood block words workmanship
Pasajes populares
Página 63 - ... no laborer, workman or mechanic in the employ of the contractor, subcontractor or other person doing or contracting to do the whole or a part of the work...
Página 128 - Electrolysis 8vo. 4 00 Fletcher's Practical Instructions in Quantitative Assaying with the Blowpipe. 16mo, mor. 1 50 Furman and Pardoe's Manual of Practical Assaying.
Página 129 - Mason's Examination of Water. (Chemical and Bacteriological.) 12mo, 1 25 Water-supply. (Considered Principally from a Sanitary Standpoint.) 8vo, 4 00...
Página 64 - ... the prevailing rate for a day's work in the same trade or occupation in the locality...