Imágenes de páginas
PDF
EPUB

Amount (estimated) required for completion of existing project.... Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix D 22.)

$17,000. 00

23. Glen Cove Harbor, New York. This harbor is an inlet on the east side of Hempstead Bay, which is accessible only at high tide, and a breakwater was needed to shelter vessels while at anchor waiting for tides.

The project for improvement, adopted in 1888, provides for a riprap breakwater about 2,500 feet long, extending in a west-southwesterly direction from the northwest corner of the Glen Cove Dock, the top to be 5 feet wide and 3 feet above mean high water, and slopes to be 1 on 1. Its estimated cost was $201,960.

Up to July 1, 1891, 824 linear feet of breakwater had been built at a cost of $22,788.23, affording a small area of shelter in shoal water close to the landing.

During the past fiscal year the breakwater was extended 232 feet farther, making its total length 1,056 feet. The cross section has been made less than designed for permanency to allow of securing more shelter with the available funds.

The project provides for about 1,450 feet extension of the breakwater, which will be built as funds for the purpose are appropriated.

July 1, 1891, balance unexpended.

June 30, 1892, amount expended during fiscal year.

July 1, 1892, balance unexpended....

July 1, 1892, outstanding liabilities

July 1, 1892, balance available..

Amount appropriated by act approved July 13, 1892.

Amount available for fiscal year ending June 30, 1893..

Amount (estimated) required for completion of existing project......... Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix D 23.)

$14,739.30

14,501.93

237.37

16.00

221.37 10,000.00

10, 221.37

156,960.00

24. Flushing Bay, New York.-Before improvement, the available depth in this broad shallow bay and in the channel leading up to Flushing was less than 4 feet at mean low water.

The project for improvement, adopted in 1879, contemplated building 16,700 feet of diking to form a tidal basin, which, by filling and discharging through the main channel, would maintain a channel depth of 6 feet or more at mean low water, after once dredging; the bottom is soft mud. The estimated cost of this work was $173,500.

In 1888 the project was modified to omit part of the diking, which then appeared unnecessary, and in 1891, at the request of many citizens, the extension of dikes was wholly omitted from the project.

Up to July 1, 1891, $89,612.08 had been expended in building 4,663 linear feet of diking, and in dredging and redredging to make and maintain a channel of 6 feet depth at mean low water. The channel is of great use to the commerce of the bay; it will probably require annual dredging to maintain it.

During the past fiscal year 73,849 cubic yards of mud was removed, making a 6-foot channel 90 feet wide and about 5,200 feet long; the depth actually made was somewhat greater, to allow for filling in.

It is proposed to apply future appropriations to d. edging, to maintain and widen the 6-foot channel,

July 1, 1891, balance unexpended

June 30, 1892, amount expended during fiscal year

July 1, 1892, balance unexpended ..

Amount appropriated by act approved July 13, 1892

Amount available for fiscal year ending June 30, 1893

Amount (estimated) required for completion of existing project ..... Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix D 24.)

$15,500. 02 15, 217.38 282.64 10,000.00

10, 282. 64

58,500.00

25. Patchogue River, New York.-This is a shallow tidal inlet extending about a mile northward from the shore of Great South Bay, Long Island, to the village of Patchogue. The natural depth in the stream and over a bar at the mouth was from 2 to 3 feet at mean low water, and the rise of tide is about 1 foot.

In 1880, and again in 1886, examinations were made by order of Congress, and subsequently a project was adopted for making a channel, 6 feet deep at mean low water and 60 feet wide, up to the village wharves, to be protected at the mouth by a jetty on the west side, at an estimated cost of $40,000.

Up to July 1, 1891, $1,541.18 (including outstanding liabilities) had been expended in building 150 linear feet of the shore end of the jetty. During the past fiscal year 1,190 linear feet of the jetty were built, making its length 1,340 feet; and a channel, 6 feet deep and 50 feet wide, was dredged from deep water in Great South Bay to and inside the entrance to the river; this channel will require partial redredging to make it permanent. It does not yet extend far enough up the river to be of great use to navigation.

Future appropriations will be applied mainly to dredging.

[blocks in formation]

Amount (estimated) required for completion of existing project..... Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix D 25.)

$14,843, 82 13, 584.83

1,258.99 77.37

1, 181. 62 8,000.00

9, 181.62

17, 000.00

26. Browns Creek, Sayville, New York.-This is a narrow stream extending northward from Great South Bay to the Sayville highway bridge, above which it is wholly a fresh-water creek. The natural depth in the creek is from 1 to 3 feet at low tide, and on a bar at the mouth it is less than 1 foot.

A survey was made by order of Congress in 1889, and a project was adopted for making the creek 100 feet wide and 4 feet deep at mean low water, the entrance channel to be protected by riprap jetties on either side, at a total estimated cost of $46,000.

The total amount appropriated for this work is $17,000.

July 1, 1891, a contract had been entered into for commencing the jetties but work had not been begun.

During the past fiscal year 492 feet of the west jetty was built and

450 feet of the east jetty partly built, under a contract not yet completed.

A channel 100 feet wide and 4 feet deep at mean low water was dredged from deep water in Great South Bay, extending between the jetties and up the stream; the total length of channel is 1,450 feet, and total amount dredged 23,194 cubic yards. In addition, privaté channels have been dredged into the marsh on the east side of the main channel, with width of 25 and 50 feet and aggregate length of 1,500 feet.

Prior to 1891 this creek was of no value for purposes of navigation. It is now quite extensively used by boats engaged in oystering, etc. Future appropriations will be applied to maintaining and extending the dredged channel and to such repairs and extension of the jetties as become necessary,

July 1, 1891, balance unexpended..

June 30, 1892, amount expended during fiscal year..

$11,929. 16 10, 457. 76

July 1, 1892, balance unexpended

1,471. 40

July 1, 1892, outstanding liabilities

July 1, 1892, amount covered by uncompleted contracts.

$537.60
560.00

1,097. 60

[blocks in formation]

Amount (estimated) required for completion of existing project...... Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix D 26.)

373.80 5,000.00

5, 373.80

29,000.00

IMPROVEMENT OF HUDSON RIVER; OF HARBORS AT SAUGERTIES AND RONDOUT, AND WAPPINGER CREEK; OF NEW YORK HARBOR AND RIVERS AND HARBORS IN ITS VICINITY, NEW YORK; AND OF RARITAN BAY, NEW JERSEY.

Officer in charge, Lieut. Col. G. L. Gillespie, Corps of Engineers, having under his immediate orders Lieut. Harry Taylor, Corps of Engineers, to November 2, 1891, and Lieut. James G. Warren, Corps of Engineers, since August 12, 1891.

1. Hudson River, New York.-The improvement of this river has been restricted by the wording of the appropriation acts to that part of it lying between Troy, at the head of navigation, 6 miles above Albany, and New Baltimore, about 14 miles below Albany.

Before the improvement was begun the navigable depth in the channel between New Baltimore and Albany was 73 feet at mean low water; between Albany and Troy, 4 feet.

The mean range of tides at State dam at Troy is 0.80 feet; at Albany, 2.32 feet; and at New Baltimore, 3.42 feet.

The plan of improvement adopted in 1867 proposed making the navigable depth between New Baltimore and Albany 11 feet, and between Albany and Troy 9 feet. This was to be accomplished by the construction of longitudinal dikes to direct the currents, and by dredging.

The estimated cost of making this improvement, prepared in 1882, subject to be increased annually, was $1,078,304. In 1889 the estimated cost was $1,424,435.

The amount expended to June 30, 1891, inclusive of outstanding liabilities, was $1,162,011.70, of which sum a large part has, however, from

the necessities of the case, been applied partly to the repair of decaying dikes and partly to dredging. At that date the dikes provided for in the project of improvement, so far as built, had resulted in securing a channel depth of 10 feet nearly all the way from New Baltimore to Albany, and of 8 feet nearly all the way from Albany to Troy. The shoal spots make the navigable depths on those parts of the river 9 feet and 7 feet, respectively.

The amount expended during the fiscal year ending June 30, 1892, inclusive of outstanding liabilities, was $96,962.43, and was applied to the repairs of the dikes; to the construction of new dikes; to dredg ing at Fish House, Bogart Light, Winnies, and Washington bars; to the removal of Dettingers Rock, opposite Van Wies Point; to the partial removal of the Overslaugh Rock, above Van Wies Point, and to the removal of wrecks from navigable channel under improvement. The river and harbor act approved September 19, 1890, provides as follows:

That the Secretary of War is authorized and directed to appoint a board of three officers of the Corps of Engineers, United States Army, whose duty it will be to thoroughly examine the obstructions to navigation in the Hudson River, between New York City and the State dam at Troy, New York, and report a project and estinate of the cost of widening and deepening said river between New York City and the city of Albany, and also between New York City and the State dam at the city of Troy for the navigation of sea-going vessels drawing twenty feet of water, and also a separate estimate of the expense of improving the river between Coxsackie and the State dam at Troy, to such an extent as to secure a navigable channel twelve feet deep at mean low water. Said board shall accompany their report with a statement as to the usefulness of such improvements and of their relations and value to commerce, and of the advisability of entering upon the same at this time; and the Secretary of War shall transmit said reports to Congress with his own views and those of the Chief of Engineers, United States Army, thereon; and the expenses of said board shall be paid out of the appropriation made in this act for the improvement of the Hudson River, not to exceed ten thousand dollars.

The Board of Engineers, authorized and directed by the above law, completed the duty assigned it, and its report, dated October 1, 1891, which was concurred in by the Chief of Engineers and the Secretary of War, was transmitted to Congress and printed as House Ex. Doc. No. 23, Fifty-second Congress, first session. A copy is also herewith submitted, accompanying annual report of the officer in charge upon the improvement of Hudson River (Appendix E 1).

Three propositions looking to improvement of the navigation of the river were by the terms of the act to be considered by the Board and projects, with estimates of cost, required to be submitted.

(1) Between New York City and the city of Albany, for the navigation of seagoing vessels drawing 20 feet of water.

(2) Between New York City and the State dam at Troy, for the navigation of seagoing vessels drawing 20 feet of water.

(3) Between Coxsackie and the State dam at Troy, for navigable channel 12 feet deep at mean low water.

Upon these three several propositions the Board, after full and careful consideration, remarks as follows:

Concerning the first two-deep channels between New York City and Albany and between New York City and Troy

The Board is of the opinion that the possible benefits to commerce to be derived from the proposed improvement for vessels drawing 20 feet are not, under existing conditions, sufficient to justify at this time the expenditure necessary to make such improvement.

The estimates of cost of carrying out the two projects contained in the said act, which provide for widening and deepening the channels between New York City

and the city of Albany and between New York City and the city of Troy for the navigation of seagoing vessels drawing 20 feet of water, are $5,934,847.60 and $19,507,832.74, respectively.

Concerning the third-channel 12 feet deep between Coxsackie and the State dam at Troy

After carefully studying the wants of commerce, the Board is of the opinion that the third project contained in the act of September 19, 1890, which provides for improving the Hudson River "between Coxsackie and the State dam at Troy to such an extent as to secure a navigable channel 12 feet deep at mean low water,” is a worthy and useful one, and accordingly recommends it for adoption.

[blocks in formation]

In view of the necessities of the commerce incident to the river proper and its tributary country, the Board is of the opinion that the project for improvement adopted in 1867 should be extended so as to provide for a channel depth of at least 12 feet at mean low water, and that such an extension is well worth the expenditure required for its execution.

The estimate submitted by the Board for a channel 12 feet deep and 400 feet wide from Coxsackie to the foot of Broadway, Troy, and thence 12 feet deep and 300 feet wide to the State dam at Troy, is $2,447,906.56. July 1, 1891, balance unexpended................

June 30, 1892, amount expended during fiscal year.

$128, 342. 71

87, 228.98

July 1, 1892, balance unexpended....

July 1, 1892, outstanding liabilities

41, 113. 73

$9,733. 45

July 1, 1892, amount covered by uncompleted contracts..

[blocks in formation]

July 1, 1892, balance available

Amount appropriated by act approved July 13, 1892.

20, 133. 53 187,500.00

Amount available for fiscal year ending June 30, 1893..

207,633.53

Amount (estimated) required for completion of existing project......2, 260, 406. 00 Amount that can be profitably expended in fiscal year ending June 30, 1894

Submitted in compliance with requirements of sections 2 of river and harbor acts of 1866 and 1867.

(See Appendix E 1.)

500,000.00

2. Harbor at Saugerties, New York. This harbor is formed by the mouth of Esopus Creek, which empties into the Hudson River, on the west bank, about 100 miles above New York City.

The bar at the entrance at the time of original examination, made in November, 1883, with the view of preparing estimates for improvement, had a navigable depth of 3 feet only at mean low water, and the distance between the 6-foot curves across it was 1,100 feet. The harbor could therefore be entered only at high water even by the smallest class of vessels. The range of tides is 4 feet, approximately.

The plan of improvement which was adopted in 1887 provided for securing a depth of 8 feet, mean low water, from the entrance to the head of navigation, 13 miles, by the construction of two parallel dikes, each 2,300 feet long, 260 feet apart on the inside and 280 feet apart on the outside, and by dredging, if found necessary, 30,000 cubic yards of material from the channel between the dikes.

The estimated cost of the improvement was $52,000; the amount expended upon the project up to the close of the fiscal year ending June 30, 1891, inclusive of outstanding liabilities, was $36,299.11. At that date the south dike had been completed, and its length was 2,363 feet; the north dike had been completed for a length of 809 feet, and the shoal in front of Sheffield's paper mill had been dredged to afford a channel 50 feet wide and 7 to 8 feet deep, mean low water. The chan-*

« AnteriorContinuar »