cated about 20 feet to its water line below the street surface. excavation is expected to be largely in sand, gravel and clay, with considerable water.

The contract was made November 27, 1907. On account of the severe weather of the winter, the Board permitted the contractor to delay starting on this work until March 1, 1908.

A second contract, extending from Kendall Street, through Cypress Street, to Boylston Street, a distance of 1,275 feet, was made with the Hugh Nawn Contracting Company on November 25, 1907. Of this length, 940 feet will be in tunnel, in earth and Roxbury puddingstone, and 335 feet in open trench. Work in the open cut section was started December 2, 1907, on the south side of Boylston Street. At the date of this report 130 feet of trench have been excavated to grade. The excavation at this location has a depth of about 25 feet, -20 feet in sand, gravel and clay. The bottom 5 feet is in Roxbury pudding-stone. The excavation has been handled by bucket excavators. Considerable water has been found in excavation.

A shaft about 12 feet square for tunnel heading was started December 5, 1907, at the corner of Kendall and Cypress streets. At the date of this report the shaft has been completed to a depth of about 35 feet, and a tunnel heading started in a northerly direction.

The sewer along the whole length of this section is to be of horseshoe cross-section, 7 feet high and 6 feet 6 inches wide. The masonry walls of the sewer are to be of Portland concrete, from 12 inches to 15 inches in thickness. At the date of this report no masonry has been placed in the section.

Section 82, Brookline.

Division Engineer in Charge.— FRANK I. CAPEN.

Contractors. T. J. O'CONNELL, Contract No. 57 (Sta. 030 to 13 + 50). T. J. O'CONNELL, Contract No. 55 (Sta. 30+50 to 48 +50). JAMES DRISCOLL & SON, Contract No. 56 (Sta. 13 + 50 to 30 + 50).

This section extends from Boylston Street, along Cypress Street, Brington Road, private lands, Brookline Playground, Davis and Gorham avenues, Greenough, Washington and Park streets, to Beacon Street, a distance of 4,830 feet.

Three contracts have been made for this construction; one extending from Boylston Street to Davis Avenue, with T. J. O'Connell, dated July 9, 1907, for a length of 1,320 feet. Work on this con

tract was begun July 18, at Davis Avenue. The excavation had an average depth of 18 feet, in sand, gravel and clay. In the Brookline Playground, for a length of about 200 feet, very fine sand was encountered. Not a large amount of water was found in the excavation. It was handled by a 4-inch centrifugal pump, electrically operated at a well on Davis Avenue. This pump controlled the ground waters to the crossing of the Boston & Albany Railroad. The excavation was handled by bucket excavators from Davis Avenue to the railroad. The excavation under the railroad and Village Brook was made without the aid of machinery. Through private lands and Brington Road the excavation was handled by bucket excavators, to near Cypress Street. In Cypress Street and for a short length in Brington Road, Roxbury pudding-stone was found for a depth of about 6 feet at the bottom of the trench. This rock excavation was found for a length of about 150 feet, and over this length of trench the excavation was handled by a framed derrick on platform.

No large amount of water was found in the excavation between Boylston Street and the railroad. It was handled from a well on private lands near Brington Road by a 4-inch centrifugal pump, electrically operated. The excavation on this length of the section was completed about the middle of December.

The sewer for this length is 6 feet 6 inches wide and 7 feet high, of horseshoe cross-section. It is built of Portland concrete, with walls about 12 inches in thickness. Passing under the branch of the Boston & Albany Railroad the masonry was increased to about 16 inches in thickness and reinforced with twisted steel. Passing under Village Brook the section was widened to 8 feet and the arch depressed so that the sewer had a height of 5 feet and 6 inches. The walls of the sewer were increased to 16 inches in thickness and the section reinforced with twisted steel.

For a length of about 100 feet, in Brington Road, the local 8-inch sewer was relaid on the side of the Metropolitan Sewer. The masonry was completed on this contract and trenches backfilled late in December. On account of the severe winter conditions, repairs to surfaces of streets and in private lands will be made in the spring.

A second contract, for construction of part of this section, was made with James Driscoll & Son, on May 21, 1907, for a length of 1,700 feet, in Gorham Avenue, Greenough and Washington streets,

[graphic][ocr errors][merged small][merged small]

TRENCH MACHINE IN OPERATION ON CYPRESS STREET, BROOKLINE-HIGH LEVEL SEWER EXTENSION.

« AnteriorContinuar »