The Elements of Specification Writing: A Text-book for Students in Civil EngineeringJohn Wiley & Sons, Incorporated, 1913 - 125 páginas |
Dentro del libro
Resultados 1-5 de 18
Página 2
... agreed percentage of profit . ( ii ) Cost - plus - a - fixed - sum . This varies from ( i ) simply in that the amount added is a prearranged sum , not a pre- arranged fraction of the cost . It may be said of the day's work plan ...
... agreed percentage of profit . ( ii ) Cost - plus - a - fixed - sum . This varies from ( i ) simply in that the amount added is a prearranged sum , not a pre- arranged fraction of the cost . It may be said of the day's work plan ...
Página 6
... agreed . Every contract springs from the acceptance of an offer . Each party must have , however , understood and assented to the offer in precisely the same sense . When it can be shown that either entered into the agreement through ...
... agreed . Every contract springs from the acceptance of an offer . Each party must have , however , understood and assented to the offer in precisely the same sense . When it can be shown that either entered into the agreement through ...
Página 41
... herein contained , and the plans herein referred to , may be modified and changed from time to time as may be agreed in writing between the parties hereto , in a manner not materially SPECIFICATIONS AND PLANS 4I Alterations.
... herein contained , and the plans herein referred to , may be modified and changed from time to time as may be agreed in writing between the parties hereto , in a manner not materially SPECIFICATIONS AND PLANS 4I Alterations.
Página 42
... agreed to be done and performed . ( B ) The right is reserved by ( the Owner ) to make such changes in the plans and specifications as may from time to time appear necessary or desirable and as may be recommended by the Engineer , and ...
... agreed to be done and performed . ( B ) The right is reserved by ( the Owner ) to make such changes in the plans and specifications as may from time to time appear necessary or desirable and as may be recommended by the Engineer , and ...
Página 43
... agreed that these specifications and the accompanying plans are intended to coöperate , so that any matter or thing shown by one and not by the other shall be of the same effect as if contained in or shown by both and shall be performed ...
... agreed that these specifications and the accompanying plans are intended to coöperate , so that any matter or thing shown by one and not by the other shall be of the same effect as if contained in or shown by both and shall be performed ...
Contenido
15 | |
16 | |
17 | |
22 | |
23 | |
25 | |
26 | |
27 | |
28 | |
29 | |
31 | |
32 | |
35 | |
38 | |
39 | |
41 | |
42 | |
44 | |
46 | |
47 | |
52 | |
53 | |
54 | |
55 | |
56 | |
57 | |
58 | |
71 | |
73 | |
75 | |
77 | |
82 | |
83 | |
84 | |
91 | |
93 | |
96 | |
98 | |
101 | |
104 | |
105 | |
106 | |
108 | |
109 | |
111 | |
112 | |
113 | |
114 | |
121 | |
122 | |
123 | |
124 | |
125 | |
Otras ediciones - Ver todas
Términos y frases comunes
50 Small 8vo Advertisement aforesaid agreed amount Analysis arbitration bidder bids bond bridge building Catskill Aqueduct cement cent Chapter Chemistry City Civil Engineers claim completion concrete construction contract Contractor cost courts cubic yard Deduct delay Descriptive Geometry Design Electrolysis employees Engineer's Engineering Record estimate excavation expense extra finished furnished Geometry grades guarantee hardpan hereby Khammurabi labor lien liquidated damages Loose Leaf maintenance Manhattan bridge Manual masonry materials ment method Municipal Engineering necessary ordinances otherwise Owner paid parties patent pavements payment penalty percentage performance person pipe plans and specifications practice Preparation proper Railroad reason Reference retained Riprap rock sewer specific clauses specifica standard steel stipulated stone Strength of Materials structure student subcontractor sublet surety bond thereof tions tract tractor tunnel unit prices Water Williamsburg Bridge wood block words workmanship writing
Pasajes populares
Página 59 - ... no laborer, workman or mechanic in the employ of the contractor, subcontractor or other person doing or contracting to do the whole or a part of the work...
Página 1 - Large 8vo, 6 00 KEEP — Cast Iron 8vo, 2 50 KING— Elements of the Mechanics of Materials and of Power of Transmission 8vo, *2 50 LANZA — Applied Mechanics 8vo, 7 50 LOWE — Paints for Steel Structures 12mo, 1 00 MAIRE— Modern Pigments and their Vehicles 12mo, 2 00 MAURER — Technical Mechanics 8vo, 4 00...
Página 2 - Health 12mo. 1 50 Gerhard's Guide to Sanitary Inspections 12mo, 1 50 • * Modern Baths and Bath Houses 8vo, 3 00 Sanitation of Public Buildings 12mo, 1 50 * The Water Supply, Sewerage, and Plumbing of Modern City Buildings. 8vo. 4 00...
Página 2 - Fisher's Table of Cubic Yards Cardboard, 25 Godwin's Railroad Engineers' Field-book and Explorers
Página 5 - Turbine 8vo, 4 00 Peabody's Manual of the Steam-engine Indicator 12mo, 1 50 Tables of the Properties of Steam and Other Vapors and TemperatureEntropy Table 8vo, 1 00 Thermodynamics of the Steam-engine and Other Heat-engines. . . .8vo.
Página 5 - General Method for the Identification of Pure Organic Compounds. Vol. I. Compounds of Carbon with Hydrogen and Oxygen. Large 8vo, 5 00 Vol. II. Nitrogenous Compounds. (In Preparation.) Vol. III. The Commercial Dyestuffs Large 8vo, 5 00 * Nelson's Analysis of Drugs and Medicines 12mo, 5 00 Ostwald's Conversations on Chemistry.
Página 10 - Metcalfe's Cost of Manufactures, and the Administration of Workshops. .8vo, 5 00 Putnam's Nautical Charts 8vo, 2 00 Ricketts's History of Rensselaer Polytechnic Institute 1824-1894. Large 12mo, 3 00...
Página 2 - Richey's Handbook for Superintendents of Construction 16mo, mor. 4 00 Building Foreman's Pocket Book and Ready Reference. . 16mo, mor. 5 00 * Building Mechanics' Ready Reference Series: * Carpenters' and Woodworkers' Edition 16mo, mor. 1 50 * Cement Workers' and Plasterers