Imágenes de páginas
PDF
EPUB

APPENDIX.

SPECIFICATIONS FOR PAVING STREETS WITH SHEET ASPHALT AND BITUMINOUS MACADAM.

1. Work.-The work to be done under this contract will consist of paving with sheet asphalt such streets, avenues, and roads in the District of Columbia, or parts thereof, or doing any portion of such work as may be ordered in writing by the Commissioners of the District of Columbia under appropriation for the fiscal year ending June 30, 1913. The estimated amount is 21,000 square yards of asphalt surface and 1,700 square yards of vitrified block gutter, 6,000 square yards of bituminous macadam on a concrete base and 5,000 square yards of bituminous macadam on a broken-stone base. These amounts are approximations only and may be considerably varied from, but they will be used in canvassing bids, and the awards will be based thereon. One award will be made to the lowest acceptable bidder for all the asphalt pavement including their vitrified block gutters and another award to the lowest acceptable bidder for all the bituminous macadam (items 3 and 4 of the proposal). The commissioners especially reserve the right to regulate the time and order of executing work ordered under this contract as may appear most advantageous to the interests of the District.

2. Bids. The contractor will, for the prices bid, do all the work prescribed in these specifications; do all the necessary grading and trimming of the roadbed and all rolling; provide bridges, fences, and other means of maintaining travel on intersecting streets, roads, and railroads, and all private driveways after giving due notice to parties affected thereby; maintain the same in good and safe condition as long as may be necessary, and then remove such temporary expedients and restore such roads to their proper condition; provide watchmen, red lights, fences, and other precautionary measures necessary to the protection of persons and property; furnish all materials (except as specified) and all tools and implements, labor, and transportation required to lay and put in complete order for use the specified pavement; and do each and all of these to the satisfaction of the engineer. Upon the completion of the work he will remove any temporary structures erected during the progress of the work and restore all fixtures, pavements, and parkings, both public and private, to satisfactory condition. 3. Grading and subgrade for concrete base. The area over which the pavement is to he laid must be excavated to the proper depth below the surface of the pavement when completed, any objectionable or unsuitable matter below the bed being removed to such depths as may be directed by the engineer and the space filled with suitable material thoroughly compacted. The bed, after being trimmed so as to be parallel to the surface of the pavement when completed, will be thoroughly compacted by rolling with a roller weighing not less than 5 tons and by heavy ramming at places which can not be reached by the roller, dampening the bed before rolling and ramming, if required, to the satisfaction of the engineer. No extra allowance will be made for trimming or rolling, but the volume of earth, etc., removed will be paid for as grading of its class.

6. Concrete base.-Upon the bed thus prepared there will be laid a 6-inch foundation of concrete as directed, made of the following materials, by volume: 1 part Portland cement, 3 parts sand, 7 parts gravel.

Broken stone, run of the crusher, may be substituted for part or all of the gravel at the option of the contractor.

5. Cement. The cement used will be a standard brand of Portland cement, uninjured by age or exposure, and delivered at the work in original undamaged packages. The cement used shall conform to the current specifications for supplying cement of its kind to the engineer department of the District of Columbia and shall be subjected to such tests as are prescribed by Circular No. 33 of the Bureau of Standards, United States Government specifications for Portland cements. The contractor shall keep the cement in store, under proper cover, in the city of Washington, and shall properly protect it until used. The engineer shall have the right to test the cement as he judges necessary and to reject any or all lots. The cement, after being accepted, can not be transferred or used by the contractor on other work without the consent of the engineer commissioner. No cement shall be used upon the work until it has been tested in the office of the engineer commissioner and accepted by him, the tests to

extend over such length of time as the engineer commissioner may think necessary. The cement while in storage or upon the work or while being hauled upon the work shall be properly protected, and no cement shall be used which, in the opinion of the engineer commissioner, has been injured by age or exposure. The cement shall be kept by the contractor in store, under proper cover, in the city of Washington, subject to inspection for at least 40 days after notifying the inspector of asphalt and cements before it can be used on the streets, if deemed advisable by the engineer commissioner. Should the contractor's work be delayed by his failure to keep himself supplied with the necessary amount of approved cement, the District shall have the right to furnish him with tested cement from the stock on hand at its warehouse and charge said contractor with the cost of same at the rate of $1.50 per barrel of Portland cement for each and every barrel so furnished and collect the amount due therefor from any moneys found to be due to said contractor by the District.

6. Sand. The sand used shall be clean, sharp river or pit sand, containing both fine and coarse grains, but free from sewage, mud, clay, mica, paper, leaves, chips, and other foreign matter and not showing when shaken with water and after subsidence more than 5 per cent, by volume, of silt.

7. Broken stone.-Stone used in concrete must be hard, durable, and properly broken to a size small enough to pass through a ring 2 inches in diameter when the run of the crusher is substituted for gravel. The run of the crusher shall not contain over 1 per cent of material passing a No. 10 sieve. The stone shall be thoroughly cleansed from all foreign substance and shall be screened and washed, if so ordered by the engineer. Sand, detritus, or any material other than hard, angular fragments of stone will be considered foreign substances.

8. Gravel.-Gravel shall be clean, washed gravel, and shall not contain pebbles greater than 2 inches in their largest dimensions and shall run from that down to pea size, well graduated.

9. Water-Water used for mortar and concrete shall be fresh and clean, free from earth, dirt, or sewage, and shall be used in such quantity as the engineer may direct. 10. Platforms-Platforms shall be provided upon which all sand, gravel, and broken stone for concrete shall be placed when brought upon the line of the work and kept there until used.

11. Mixing. The thorough mixing and incorporation of all materials will be insisted upon. If done by hand labor the dry cement and sand shall be turned over and mixed with shovels by skilled workmen not less than six times before the water is added; the stone or gravel, after being drenched with water, shall be added to the mixed sand and cement; the drenching shall not be done while the stone or gravel is in the wheelbarrow; the whole mass shall be thoroughly turned over with shovels, not less than four times, and mixed upon a water-tight platform until every particle of stone or gravel is completely enveloped with mortar. The whole operation of mixing and laying each batch shall be performed as expeditiously as possible, by the aid of machinery or a sufficient number of skilled men. If the concrete is mixed in batches requiring 1 barrel of cement, the platform must not be smaller than 10 feet by 12 feet, nor will a larger amount of concrete than can be made with 1 barrel of cement be allowed to be mixed in one batch by hand. In mixing by machinery the materials must be so delivered as to insure a uniform product of the specified proportions of all ingredients to the satisfaction of the engineer.

12. Setting.-Concrete shall nor be used after it has begun to show evidence of setting. No concrete which has once set shall be used as material for mixing a new batch.

Each batch of concrete after being mixed shall be spread in place in horizontal layers by means of shovels so as to give the requisite thickness after being tamped, and shall then be thoroughly compacted. Any evidence of lack of compaction will be regarded as sufficient reason for removal and replacement of the base. Hauling over base less than three days old must not be allowed unless planks are laid.

13. Binder. The binder course shall be composed of clean, broken stone, equal in quality to the stone for the base, and passing a 14-inch screen. Eighty-five per cent of this shall pass said screen in its longest dimensions, and of the remaining 15 per cent no piece shall have a larger dimension than 14 inches, and the stone, after passing the heating drums, shall not contain less than 5 nor more than 15 per cent of material passing a No. 10 screen.

The stone will be heated not higher than 350° F., in suitable appliances. It is then to be throughly mixed by machinery with asphalt cement, such as is acceptable for surface cement, penetration 60 to 90, at such temperature and in such proportions that the resulting binder will have life and gloss without an excess of cement. Should it appear dull from overheating or lack of cement, it will be rejected. While hot it will be hauled upon the work, spread upon the base so that when compacted it will

be at least 11 inches in thickness, and immediately rammed and rolled until it is cold. Should the resulting course not show a proper bond, it must be immediately removed and replaced by and at the expense of the contractor. Binder and top shall not be taken from the yard to the site of the work when weather conditions are, in the judgment of the engineer, unsuitable for the work of laying the pavement.

The contractor shall not enter upon a concrete base in order to lay the binder course until it has obtained sufficient strength for such a purpose, and during the period between laying the base and binder he shall properly protect it, and, when ordered by the engineer, shall sprinkle it in warm weather between the hours of sunset and sunrise as often as may be deemed necessary, and in cold weather cover it with a material suitable for its protection.

14. Asphalt wearing surface.-The wearing surface of the pavement shall be composed of asphalt, petroleum oil, asphalt cement, clean, sharp-grained sand, and fine absorbent mineral dust.

15. Asphalt. The asphalt shall be refined until homogenous and free from water and shall not at any time be heated to a temperature high enough to injure it. The refined product shall contain at least 90 per cent of bitumen soluble in carbon bisulphide and 100 parts shall not require more than 30 parts of the flux to produce the asphalt cement described in paragraph 17.

16. Petroleum oil. The oil in use in the manufacture of asphalt cement shall be a petroleum from which the lighter oils have been removed by distillation without cracking, until the oil has the following characteristics:

Free from water and foreign matter.

Flash point, not less than 300° F.

Distillate at 400° for 30 hours, less than 10 per cent.

The flash point shall be taken in a New York State closed oil tester.

The distillate shall be made with about 50 grams of oil in a small glass retort, provided with a thermometer and packed entirely in asbestos. The residue in the retort after distilling, must be fluid at 75° F., and not coarsely crystalline on cooling.

Any other softening agents fulfilling the above tests, and approved by the engineer commissioner, may be used in place of petroleum oil.

17. Asphalt cement. The asphalt cement must be of refined asphalt, fluxed when necessary with petroleum residuum, asphaltic oil, refined maltha, or other approved flux. The cement must be practically free from water and must be within the range of 40 and 70 penetration when tested at 77° F. on Dow penetration machine with No. 2 needle, 100 grams, 5 seconds. The degree of penetration to be fixed by the engineer commissioner.

Preference will be given to an asphalt cement that is not readily affected by the action of water, provided it is satisfactory in other respects. If an asphalt cement is accepted that is affected by water some provision satisfactory to the engineer commissioner must be made to guard against the results of such action, and such work must be included in the price bid. The use of an asphalt under these specifications shall be subject to the approval of the engineer commissioner, and if an asphalt has been proposed for use by the contractor and approved by the engineer commissioner no change in the asphalt to be used shall be made unless with the approval of the engineer commissioner. If an asphalt or flux is submitted for use which has not been successfully used for a period of at least two years for paving under conditions similar to those existing in the District of Columbia, its use may be limited to such extent as may be deemed advisable, or it may be rejected for use entirely in the discretion of the engineer commissioner.

The bitumen of the asphalt cement must comply with the following tests:

1. It must be of such consistency that when tested at 32° F. it will not show a hardness below 10 penetration, and when tested at 115° F. it will not be softer than 350 penetration.

2. When a briquet of the bitumen having a minimum cross section of 1 square centimeter, having a penetration of 50° to 53° at 77° F. is tested for ductility at 77° F., the bitumen must stretch at the rate of 5 centimeters per minute to a distance of 15 centimeters before breaking.

3. When the bitumen is heated in an open tin box inch deep by 24 inches in diameter at a temperature of 300° F. for 18 hours in a hot-air oven, it must not show a loss by volatilization of over 5 per cent and it must not have been hardened over 50 per cent by this heating.

The asphalt cement must never be heated to a temperature that will injure it. When the asphalt cement contains over 5 per cent of material that will separate by subsidence while in a molten condition, it must be thoroughly agitated before drawing from storage and while in use in the supply kettles so as to insure a uniform cement. These properties shall be determined by tests made by uniform methods, descriptions of which are on file in the office of the engineer commissioner.

18. Sand. The sand in use shall be free from mud, hard grained, and moderately sharp. On sifting, it should have at least 15 per cent of material that would be caught on a 40 mesh per inch screen, 25 per cent of material that will pass an 80 mesh to the inch screen, and 10 per cent at least must pass a 100 mesh to the inch screen. If the sand to be used does not contain the desired fine material, mineral dust can be added to make up the deficiency, and in any case at least 5 per cent of such mineral dust shall be used. The amount of fine material may be increased or diminished on streets of light traffic at the discretion of the engineer commissioner.

19. Mineral dust. This shall be any fine hydraulic cement or limestone dust, the whole of which shall pass a 30-mesh screen, and at least 85 per cent pass a 100-mesh

screen.

20. Asphalt paving mixture.-The materials complying with the above specifications shall be mixed in proportion by weight depending upon their character and the traffic on the street and upon the character of the asphalt, and will be determined by the engineer commissioner, but the percentage of bitumen in any mixture soluble in carbon bisulphide shall not exceed the limits, 9 to 13 per cent. If the proportions of the mixture are varied in any manner from those specified, the mixture will be condemned; its use will not be permitted, and, if already placed on the streets, it must be removed and replaced by proper materials at the expense of the contractor.

The sand, or the mixture of sand and stone dust, and the asphaltic cement, will be heated separately to about 300° F. The dust, if limestone, will be mixed while cold with the hot sand in the required proportions and then mixed with the asphaltic cement at the required temperature, and in the proper proportion in a suitable apparatus, so as to effect a thoroughly homogeneous mixture. Sand boxes and asphalt gauges will be weighed in the presence of inspectors as often as may be desired.

Samples of all material entering into the composition of the pavement shall be supplied to the inspector of asphalt and cements when required in suitable tin boxes and cans; he shall have access to all branches of the works at any time, and shall have the right to obtain samples of all materials from the source of supply.

The pavement mixture prepared in a manner thus indicated will be brought to the ground in carts or wagons at a temperature of not less than 250° or more than 350° F.; the contractor must provide canvas covers for use in transit. It will then be shoveled into place and thoroughly spread to a thickness of at least 24 inches by means of hot iron rakes in such manner as to give uniform and regular grade, so that, after having received its ultimate compression, it will have a net thickness of at least 14 inches. This depth will be constantly tested by means of gauges furnished by the engineer commissioner. The surface will then be compressed by hand or steam rollers, after which a small amount of hydraulic cement will be swept over it, and it will then be thoroughly compressed by a steam-roller weighing not less than 175 pounds to the inch run, the rolling being continued for not less than five hours for every 1,000 yards of surface. The street to be barricaded until the surface is cool. Barricades to remain for such length of time as deemed necessary by the engineer commissioner.

21. Hauling and grading.-(a.) The old material from the streets will be hauled to the nearest property yard or to such other point as the engineer commissioner may direct.

(b.) Lines and grades will be established by the engineer commissioner, and no work will be commenced until these are given.

(c.) Contractors are to be responsible for the proper preservation of all stakes, etc., set by the engineer for the determination of line or grade; should any such be disturbed through carelessness the cost of replacing same will be charged against the contractor at a fixed price of $2 for each point, to be deducted from any money found due at final settlement.

(d.) All material excavated of whatsoever nature is the property of the District, and will be disposed of as the engineer commissioner shall direct.

(e.) The filling will be done in layers not exceeding 12 inches in thickness, and all materials used for this purpose will be subject to approval. If improper or unsuitable material be used, it will be removed at the cost of the contractor.

(f.) All measurements will be made in place, and payments made thereon.

(g.) Should the grading involve work in both "cut" and "fill," the measurement of it will be computed on the basis of the volume of the material in place in the "cut" only; the excavated material from the "cut" section deposited in the "fill" will not be again paid for as "fill." Should the amount of cut on the street not suffice to make the necessary fill, the amount borrowed from other designated localities will be paid for as grading.

22. Laying vitrified block.-Vitrified-block gutters will ordinarily be 18 inches wide, laid on a concrete base 6 inches in depth, of the same material and proportions and laid in the same manner as prescribed in these specifications for the concrete base under asphalt pavements.

As soon as practicable after the concrete base has been laid, a dry mixture, composed of 4 parts of the sand specified in paragraph 6 and 1 part of Portland cement, thoroughly mixed, will be spread thereon, as a bed for the paving blocks, to the depth of not less than one-half inch, and regulated so as to be exactly parallel to the finished grade of the gutter.

On the bed thus prepared for them the blocks will be set on edge, with the longest dimensions at right angles to the curb, or as directed by the engineer.

The longitudinal joints of each course of blocks laid must be broken by a lap of not less than 4 inches.

The blocks will then be carefully rammed by placing a plank over several courses and ramming the plank with a heavy hammer. The ramming will be continued until the blocks reach a firm, unyielding bed and present a uniform surface, with proper grade. Any lack of uniformity in the surface or defect in the grade must be corrected by taking up and relaying the blocks.

After proper ramming the entire gutter will be thoroughly grouted with a thin, easily flowing grout, of neat natural cement.

A similar construction of block to that described for the gutters may be used adjacent to railroad tracks; the base will in that case extend to the bottom of the crossties, or at least 6 inches thick.

The blocks will be furnished the contractor at the District property yards, and must be hauled to the work at his expense.

BITUMINOUS MACADAM ON CONCRETE BASE.

23. Concrete base. The base is to conform in all respects to the specifications herein in relation to concrete base for sheet asphalt pavements.

24. Paving materials. The paving materials shall be composed of crushed traprock screenings, concrete sand, and mineral dust in the following proportions: Traprock screenings, 2 parts; concrete sand, 1 part; and mineral dust, at least 5 per cent of the above aggregate, mixed with asphaltic cement. The various constituents of the mineral aggregate and asphalt cement shall be of the same kind and conform to District specifications for such materials for the year ending June 30, 1913, as follows: 25. Trap rock. The trap rock shall be of a quality to be approved by the engineer, and shall be equal to that used by the District of Columbia for macadam roadways. The crushed stone will vary in size from 1 inch to screenings and shall be devoid of dust.

26. Sand. The sand shall be hard grained and moderately sharp. On shifting it should have at least 25 per cent of material that would be caught on a 20-mesh per inch screen, and 5 per cent of material that will pass an 80 mesh to the inch screen. If the sand to be used does not contain the desired fine material, mineral dust can be added to make up the deficiency, and in any case at least 5 per cent of such mineral dust shall be used.

27. Mineral dust.-This shall be any fine, hydraulic cement or limestone dust, the whole of which shall pass a 30-mesh screen, and at least 85 per cent pass a 100-mesh

Screen.

28. Asphalt. The asphalt shall be refined until homogeneous and free from water and shall not at any time be heated to a temperature high enough to injure it. The refined product shall contain at least 90 per cent of bitumen soluble in carbon bisulphide and 100 parts shall not require more than 30 parts of the flux to produce the asphalt cement described in paragraph 30.

29. Petroleum oil. The oil in use in the manufacture of asphalt cement shall be a petroleum from which the lighter oils have been removed by distillation without cracking, until the oil has the following characteristics: Free from water and foreign matter, flash point not less than 300° F., distillate at 400° for 30 hours, less than 10 per cent. The flash point shall be taken in a New York State closed oil tester. The distillate shall be made with about 50 grams of oil in a small glass retort, provided with a thermometer and packed entirely in asbestos. The residue in the retort, after distilling, must be fluid at 75° F., and not coarsely crystalline on cooling.

Any other softening agents fulfilling the above tests, and approved by the engineer commissioner, may be used in place of petroleum oil.

30. Asphalt cement.-The asphalt cement must be of refined asphalt, fluxed when necessary with petroleum residuum, asphaltic oil, refined maltha, or other approved flux. The cement must be practically free from water and must be within the range of 40 and 70 penetration when tested at 77° F. on Dow penetration machine with No. 2 needle, 100 grams, 5 seconds. The degree of penetration to be fixed by the engineer commissioner.

« AnteriorContinuar »