Annual Report of the Croton Aqueduct DepartmentThe Board, 1858 |
Dentro del libro
Resultados 1-5 de 94
Página 3
... inches for a 2 - foot opening , and 28 inches for a 2 - foot 4 - inch opening . 3.1.1.2 Height . - Height of opening shall be measured from the lower end of the jamb to the head rabbet on the frame . The height shall be 80 inches for a ...
... inches for a 2 - foot opening , and 28 inches for a 2 - foot 4 - inch opening . 3.1.1.2 Height . - Height of opening shall be measured from the lower end of the jamb to the head rabbet on the frame . The height shall be 80 inches for a ...
Página 2
... inches C1 , C2 stress factors P h ne k t a ρ σ OJ T TV wd applied load , kips spacing of uprights , inches depth of beam , back of top flange to back of bottom flange , inches depth of beam between centroids of flanges , inches diagonal ...
... inches C1 , C2 stress factors P h ne k t a ρ σ OJ T TV wd applied load , kips spacing of uprights , inches depth of beam , back of top flange to back of bottom flange , inches depth of beam between centroids of flanges , inches diagonal ...
Página 4
... inch and a chord of 1.37 inches . The combustion chambers were made of stainless steel with an outside diameter of 1.1 inches and an inside diameter of 1.0 inch . Figures 2 ( a ) and 2 ( b ) show the engine with combustion - chamber ...
... inch and a chord of 1.37 inches . The combustion chambers were made of stainless steel with an outside diameter of 1.1 inches and an inside diameter of 1.0 inch . Figures 2 ( a ) and 2 ( b ) show the engine with combustion - chamber ...
Página 6
... inches to a width of 4 feet 3 inches , at the same time thickening from a height of 7 inches to a height of 36 inches at the back end ( Figure 3 ) where the vacuum space bulges out around the pole pieces as illus- trated . Its structure ...
... inches to a width of 4 feet 3 inches , at the same time thickening from a height of 7 inches to a height of 36 inches at the back end ( Figure 3 ) where the vacuum space bulges out around the pole pieces as illus- trated . Its structure ...
Página 5
... inches --pounds 4.724 6 , 160 ___inches__ 231.1 inches . 203. 12 inches 26.1 inches__ 236 , 2 __inches__ 242 Rifling , spiral , right - hand twist , increasing from 0 to 1 turn in 600 cali- bers at breech to 1 turn in 30 calibers at the ...
... inches --pounds 4.724 6 , 160 ___inches__ 231.1 inches . 203. 12 inches 26.1 inches__ 236 , 2 __inches__ 242 Rifling , spiral , right - hand twist , increasing from 0 to 1 turn in 600 cali- bers at breech to 1 turn in 30 calibers at the ...
Otras ediciones - Ver todas
Annual Report of the Croton Aqueduct Department New York (City) Croton Aqueduct Board Vista completa - 1856 |
Términos y frases comunes
66 basins aforesaid amount appointed basins and culverts Bleecker Bowery brick Broadway broken stone Canal Catharine cents per cubic Chatham city with water commenced Commissioners Committee Common Council construction contract contractor Croton Aqueduct Board Croton Aqueduct Department Croton dam Croton river Croton Water cubic yard Dinsmore division bank dollars earth East Broad'y eight Eighth avenue engineer may deem engineer may direct estimate excavation expense exterior Reservoir bank feet in length Fifth Forsyth further agreed Greenwich and Washington Hester Houston Hudson hundred inches Jacob Sharp James James slip John July laid in cement legislature Lineal feet Manhattan Valley masonry measured in embankment Messrs metres mortar Myndert Van Schaick Nicholas Hotel Number of sewers outer bank outer slopes parties paving proposals puddle bank puddle ditches quantity Reservoir ground rock sand SCHEDULE Sept Sixth avenue specifications streets supply the city thousand William York
Pasajes populares
Página 94 - Provided, that nothing herein contained shall be construed to affect the right hereby reserved of the said...
Página 95 - Now, Therefore, the condition of the above obligation is such, that if the said shall well and truly, and in...
Página 93 - Boston, for or on account of any injuries or damages received or sustained by any party or parties, by or from the said Contractor, his servants or agents...
Página 76 - ... shall in all cases decide every question which may arise relative to the execution of this contract on the part of the said Contractor, and his estimate and decision shall be final and conclusive...
Página 76 - To prevent all disputes and litigation, it is further agreed, by and between the parties to this contract, that said engineer, shall in all cases determine the amount or the quantity of the several kinds of work which are to be paid for under this contract; and he shall...
Página 95 - ... then this obligation to be void, or else to remain in full force and virtue of law.
Página 90 - Contractor to discontinue all work, or any part thereof under this contract, by a written notice to be served upon the Contractor, either personally or by leaving said notice at his residence or with his agent in charge of the work, and thereupon the said Contractor shall discontinue said work or such part thereof.
Página 29 - ... thousand dollars, by the creation of a public fund or stock, to be called, " The Water Stock of the City of New- York," which shall bear an interest not exceeding five per cent.
Página 75 - ... may deem proper, to inspect the materials to be furnished, and the work to be done under this agreement ; and to see that the same strictly correspond with the specifications hereinafter set forth.
Página 94 - 23. And the said party of the second part further agrees that he shall not be entitled to demand or receive payment for any portion of the aforesaid work or materials until the same shall be fully completed in the manner set forth in this agreement...