Página 139
... price per lineal foot of pipes of each size laid as herein specified , and for the various depths of trench named , also for all other items enumerated in the schedule opposite , which price shall be in full for all labor and materials ...
... price per lineal foot of pipes of each size laid as herein specified , and for the various depths of trench named , also for all other items enumerated in the schedule opposite , which price shall be in full for all labor and materials ...
Página 140
... specifications hereto annexed , and the plans and drawings of the same on file in your Engineer's office , at the following prices , viz .: ITEMS . Price per lineal foot for furnishing and laying 140 THE SEPARATE SYSTEM OF SEWERAGE .
... specifications hereto annexed , and the plans and drawings of the same on file in your Engineer's office , at the following prices , viz .: ITEMS . Price per lineal foot for furnishing and laying 140 THE SEPARATE SYSTEM OF SEWERAGE .
Página 141
... Price per lineal foot for furnishing and laying 15 - inch pipe , including Ys , branches , detachable covers , and cement joints Price per lineal foot for furnishing and laying 12 - inch pipe , including Ys , branches , detachable ...
... Price per lineal foot for furnishing and laying 15 - inch pipe , including Ys , branches , detachable covers , and cement joints Price per lineal foot for furnishing and laying 12 - inch pipe , including Ys , branches , detachable ...
Página 142
... price per cubic yard .. And .. .hereby agree to enter into a contract within five days from the date of your acceptance of this proposal , to finish and complete said work ( by the .......... day of , .... ......... ) , according to the ...
... price per cubic yard .. And .. .hereby agree to enter into a contract within five days from the date of your acceptance of this proposal , to finish and complete said work ( by the .......... day of , .... ......... ) , according to the ...
Página 147
... price per lineal foot for trench . 32. The contractor shall keep the trenches free from water during the progress of the work , as no pipe of masonry shall be laid in the water . PROTECTION OF PROPERTY . 33. The contractor shall at his ...
... price per lineal foot for trench . 32. The contractor shall keep the trenches free from water during the progress of the work , as no pipe of masonry shall be laid in the water . PROTECTION OF PROPERTY . 33. The contractor shall at his ...
Otras ediciones - Ver todas
The Separate System of Sewerage, Its Theory and Construction Staley Cady 1840-,George Spencer Joint Author Pierson Sin vista previa disponible - 2016 |
Términos y frases comunes
ammonias amount assessing average back-filling bacteria branches brick sewer cent clean Combined System connected construction consumption contractor cost cubic curve dead end depth of flow diagram diem per capita discharge distance drainage effluent Engineer Excavating and Back feet per second filled filter filtration fixtures flush-tanks gallons grade horizontal house drains house sewer inches inches in diameter increased iron pipe joints laid lamp-holes length less lineal foot man-holes material maximum method necessary nitrification nitrogen obstruct ordinary organic matter outlet pipe sewers placed plumb-bob plumbing plumbing fixtures population Price per lineal proper properly pumping purified removal sand sanitary Schenectady Separate System sewage sewer gas sewer pipe sewerage shown in Plate soil pipe storm water stream street sewer subsoil Superintendent surface syphon system of sewers TABLE tank tion trap trench typhoid fever velocity ventilating pipes waste pipes ΙΟ
Pasajes populares
Página 155 - ... for or on account of any injuries or damages received or sustained by any person or persons, by or from the said contractor, his servants or agents, in the construction of said work...
Página 156 - Stevenson or to his certain attorney, heirs, executors, administrators, or assigns, to which payment well and truly to be made we bind ourselves, our heirs, executors, and administrators, and each and every of them, firmly by these presents. Sealed with our seals, and dated this 20th day of December, one thousand eight hundred and ninety.
Página 247 - ... be deemed guilty of a misdemeanor, and upon conviction thereof be fined in any sum not exceeding fifty dollars.
Página 312 - With the gravels and sands, from the coarsest to the finest, we find that purification by nitrification takes place in all, when the quantity of sewage is adapted to their ability, and the surface is not allowed to become clogged by organic matter to the exclusion of air.
Página 140 - Engineer. [INSTRUCTIONS TO CONTRACTORS.] TO CONTRACTORS. 1. All bids must be made upon the printed forms, to be obtained at the office of the Engineer, and enclosed in a sealed envelope, directed to the Engineer of Sewers and endorsed upon the outside of the envelope, Proposal for Constructing Sewers in the City of 2. Each bid must be accompanied by a deposit of Dollars, to be left in the hands of the City Clerk, subject to the conditions specified in the proposal hereto annexed, as a guarantee of...
Página 143 - NOW, THEREFORE, In consideration of the payments and covenants hereinafter mentioned, to be made and performed by said...
Página 246 - No brick, sheet metal, earthenware or chimney flue shall be used as a sewer ventilator, nor to ventilate any trap, drain, soil or waste-pipe.
Página 304 - ... 2. In order that the effluent water may not be directly polluted by the sewage liquid, the maximum supply of the latter must not be more than can be taken up by the pores of the soil. 3. Dry loamy soil absorbs more than peaty soil and gives up less, whilst dry sandy soil on the contrary absorbs less and gives up more.
Página 30 - Smith, in a very comprehensive paper on the "Influence of sewerage and water supply on the death rate in cities" writes as follows: "Data drawn from sewered cities is now available for study and comparison.
Página 154 - If such alterations diminish the quantity of work to be done they shall not constitute a claim for damages, or for anticipated profits on the work that may be dispensed with ; if they increase the amount of work, such increase shall be paid for according to the quantity of the work actually done and at prices and rates established for such work under this contract.