Página 43
... faces , parallel sides , sharp edges and angles and must be sound , hard and well burned . No brick is to be used in any part of the work which is over - burned , and all " salmon " or soft brick will be ... Face brick , where exposed 43.
... faces , parallel sides , sharp edges and angles and must be sound , hard and well burned . No brick is to be used in any part of the work which is over - burned , and all " salmon " or soft brick will be ... Face brick , where exposed 43.
Página 44
... Face brick , where exposed to view , shall be of a uniform color , and , if neces- sary , carefully culled . Such culling must be done on the ground and brick stacked up ready for use and no culling of brick by masons , when laying the ...
... Face brick , where exposed to view , shall be of a uniform color , and , if neces- sary , carefully culled . Such culling must be done on the ground and brick stacked up ready for use and no culling of brick by masons , when laying the ...
Página 48
... face after removal of the forms will not be permitted . An approved coating of pitch and felt shall then be applied to the exterior face of the foundation walls and to any other portion where it is necessary to keep out moisture . This ...
... face after removal of the forms will not be permitted . An approved coating of pitch and felt shall then be applied to the exterior face of the foundation walls and to any other portion where it is necessary to keep out moisture . This ...
Página 50
... face work of structure and other masonry constructions as are herein described or shown on the plans and as are located above a datum line established four ( 4 ) inches below the sidewalk or area way levels for exterior walls and above ...
... face work of structure and other masonry constructions as are herein described or shown on the plans and as are located above a datum line established four ( 4 ) inches below the sidewalk or area way levels for exterior walls and above ...
Página 53
... face line and superstructure , i . e . , side walk , curbing , area way , walls , coping and railings which are hereinafter described . ( b ) The building is to be divided into two sec- tions with a masonry " division wall " between the ...
... face line and superstructure , i . e . , side walk , curbing , area way , walls , coping and railings which are hereinafter described . ( b ) The building is to be divided into two sec- tions with a masonry " division wall " between the ...
Otras ediciones - Ver todas
Report A-[F] of Commission on Electric Lighting for the City of New York ... New York (N y ) Commission on Electric L Sin vista previa disponible - 2015 |
Términos y frases comunes
000 kilowatt-hours 000 kilowatts approved arc lamps arc lights basement floor blow-off boiler feed pumps boiler room Boroughs brass Bronx Brooklyn Brooklyn and Queens bulkhead busbars capacity cast iron cement central station cents City clean coal bunkers COMMISSION ON ELECTRIC Commissioner complete concrete condenser connected construction contract Contractor copper diameter doors drawings duct ELECTRIC LIGHTING Engineer equipment estimate extra heavy face brick feeders feet finished fittings flanges flue furnished galvanized gate valves grade incandescent lighting incandescent service inch intake iron pipe iron pipe size joints load located Manhattan masonry material mortar necessary nickel plated oil switches operating plant plaster plumbing Portland cement Power House pressure public buildings Report Richmond roof sash seawall specifications steam stone storage streets structural steel sub-stations superheater supply surface surge tank thick tile tion total annual cost total cost wall water closet wattmeter wrought iron York
Pasajes populares
Página 33 - ... in case of such discontinuance of the employment of the contractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense Incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor...
Página 33 - ... written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under...
Página 33 - Should the Contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work wIth promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the Architects, the Owner shall be at liberty, after three days...
Página 10 - DOLLAKS for each and every day the time consumed in said performance and completion may exceed the time hereinbefore allowed for that purpose; which said sum, in view of the difficulty of ascertaining the loss which The...