... faced in the following manner : When laying concrete in forms a 2 in . thickness of " Style A " mortar shall be deposited on the outside of the concrete by means of a metal dia- 48. Intake and Discharge Tunnels . phragm of approved form 47.
... faced in the following manner : When laying concrete in forms a 2 in . thickness of " Style A " mortar shall be deposited on the outside of the concrete by means of a metal dia- 48. Intake and Discharge Tunnels . phragm of approved form 47.
Página 53
... thick coat of genuine red lead mixed with boiled linseed oil before the parts are assembled . ( m ) When the several parts are assembled and accepted by the inspector , if inspected , such parts are to be thoroughly cleaned from all ...
... thick coat of genuine red lead mixed with boiled linseed oil before the parts are assembled . ( m ) When the several parts are assembled and accepted by the inspector , if inspected , such parts are to be thoroughly cleaned from all ...
Página 56
... thickness for top dressing , trowelled smooth and left free from defect on completion . Floors to be laid in sections where directed . Filling under granolithic top dressing is to be Style " B " mortar and gran- othlic dressing is to be ...
... thickness for top dressing , trowelled smooth and left free from defect on completion . Floors to be laid in sections where directed . Filling under granolithic top dressing is to be Style " B " mortar and gran- othlic dressing is to be ...
Página 58
... thickness not exceed- ing 3/8 in . All bricks used shall be of uniform tex- ture , hard - burned , entirely through , free from lime or other impurities . The face brick in the boiler room including those on the rear elevation , are to ...
... thickness not exceed- ing 3/8 in . All bricks used shall be of uniform tex- ture , hard - burned , entirely through , free from lime or other impurities . The face brick in the boiler room including those on the rear elevation , are to ...
Página 60
... thick . Top surface to be quarry axed and exposed surfaces to be tooled . Tem- plates to be set to the levels required to receive the steel work . If steel wall plates are used the same are to be set by the masons to the proper level ...
... thick . Top surface to be quarry axed and exposed surfaces to be tooled . Tem- plates to be set to the levels required to receive the steel work . If steel wall plates are used the same are to be set by the masons to the proper level ...
Otras ediciones - Ver todas
Report A-[F] of Commission on Electric Lighting for the City of New York ... New York (N y ) Commission on Electric L Sin vista previa disponible - 2015 |
Términos y frases comunes
000 kilowatt-hours 000 kilowatts approved arc lamps arc lights basement floor blow-off boiler feed pumps boiler room Boroughs brass Bronx Brooklyn Brooklyn and Queens bulkhead busbars capacity cast iron cement central station cents City clean coal bunkers COMMISSION ON ELECTRIC Commissioner complete concrete condenser connected construction contract Contractor copper diameter doors drawings duct ELECTRIC LIGHTING Engineer equipment estimate extra heavy face brick feeders feet finished fittings flanges flue furnished galvanized gate valves grade incandescent lighting incandescent service inch intake iron pipe iron pipe size joints load located Manhattan masonry material mortar necessary nickel plated oil switches operating plant plaster plumbing Portland cement Power House pressure public buildings Report Richmond roof sash seawall specifications steam stone storage streets structural steel sub-stations superheater supply surface surge tank thick tile tion total annual cost total cost wall water closet wattmeter wrought iron York
Pasajes populares
Página 33 - ... in case of such discontinuance of the employment of the contractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expense Incurred by the owner in finishing the work, such excess shall be paid by the owner to the contractor...
Página 33 - ... written notice to the contractor, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractor under...
Página 33 - Should the Contractor at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work wIth promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified by the Architects, the Owner shall be at liberty, after three days...
Página 10 - DOLLAKS for each and every day the time consumed in said performance and completion may exceed the time hereinbefore allowed for that purpose; which said sum, in view of the difficulty of ascertaining the loss which The...