| Michigan. Supreme Court, Randolph Manning, George C. Gibbs, Thomas McIntyre Cooley, Elijah W. Meddaugh, William Jennison, Hovey K. Clarke, Hoyt Post, Henry Allen Chaney, William Dudley Fuller, John Adams Brooks, Marquis B. Eaton, Herschel Bouton Lazell, James M. Reasoner, Richard W. Cooper - 1919 - 806 páginas
...the contractor for the said work and to enter, upon the premises and take possession of all materials thereon, and to employ any other person or persons...receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid... | |
| 1922 - 1138 páginas
...premises and take possession, for the purposes of completing the work included under this contract, of all materials, tools, and appliances thereon, and...receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the. amount to be paid... | |
| 1913 - 1236 páginas
...the contractor for the said work, and enter upon the premises and take possession of all materials thereon, and to employ any other person or persons...receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid... | |
| 1912 - 1170 páginas
...provide the materials therefor ; and In case of such discontinuance of the employment of the con. tractor he shall not be entitled to receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amouiit to be paid... | |
| 1914 - 1230 páginas
...the materials therefor; and in ease of such discontinuance of the employment of the contractors they shall not be entitled to receive any further payment under this contract until such work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under... | |
| 1908 - 1148 páginas
...and to employ any other person or persons to finish the work, and to provide the materials tlierefor, and, In case of such discontinuance of the employment...receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the whole amount to... | |
| 1908 - 1134 páginas
...any other person or persons to finish the work, and to provide the materials therefor ; and in ease of such discontinuance of the employment of the contractor...receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid... | |
| 1919 - 1050 páginas
...the materials therefor, and in case of such discontinuance of the employment of the contractor they shall not be entitled to receive any further payment under this contract, until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid... | |
| 1917 - 1322 páginas
...and appliances thereon, and to employ any other person or persons to finish the work, and to provide materials therefor ; and in case of such discontinuance...receive any further payment under this contract until the said work shall be wholly finished, at which time, ¡f the unpaid balance of the amount to be paid... | |
| Arkansas. Supreme Court - 1917 - 702 páginas
...and appliances thereon, and to employ any other person or persons to finish the work, and to provide materials therefor; and in case of such discontinuance...receive any further payment under this contract until the said work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid... | |
| |