Engineering Contracts and Specifications: Including a Brief Synopsis of the Law of Contracts and Illustrative Examples of the General and Technical Clauses of Various Kinds of Engineering Specifications, Designed for the Use of Students, Engineers and ContractorsEngineering news Publishing Company, 1895 - 417 páginas |
Dentro del libro
Resultados 1-5 de 42
Página 136
... holes for standing water , generally with a descent at bottom to allow free passage of water . Wherever the excavations furnish more material than is required for embankments , the surplus will be used to increase width of embankment ...
... holes for standing water , generally with a descent at bottom to allow free passage of water . Wherever the excavations furnish more material than is required for embankments , the surplus will be used to increase width of embankment ...
Página 160
... holes are necessary , they will be ordered by the engineer . All stones shall be prepared by dressing and hammering before they are brought on the wall , and must be so shaped that their bearing beds will be parallel to their natural ...
... holes are necessary , they will be ordered by the engineer . All stones shall be prepared by dressing and hammering before they are brought on the wall , and must be so shaped that their bearing beds will be parallel to their natural ...
Página 168
... are to be dressed , for the full depth of the stone , to surfaces , allowing of one quarter ( 4 ) inch joint at most . No plug hole of more than 6 inches across or nearer than 3 inches from an arris is to 168 ENGINEERING SPECIFICATIONS .
... are to be dressed , for the full depth of the stone , to surfaces , allowing of one quarter ( 4 ) inch joint at most . No plug hole of more than 6 inches across or nearer than 3 inches from an arris is to 168 ENGINEERING SPECIFICATIONS .
Página 169
... hole in any one joint exceed onequarter of its whole area . The stone shall be laid with one quarter ( 4 ) inch ... holes and recesses and grooves . No payment will be made for cutting grooves and recesses other than the price paid ...
... hole in any one joint exceed onequarter of its whole area . The stone shall be laid with one quarter ( 4 ) inch ... holes and recesses and grooves . No payment will be made for cutting grooves and recesses other than the price paid ...
Página 171
... holes shall be made in the face of the coping or on the pointed work of the cutwater . The stones of the curved ... hole shall be extended six inches into the lower course , a small quantity of mortar shall be put into the t hole , the ...
... holes shall be made in the face of the coping or on the pointed work of the cutwater . The stones of the curved ... hole shall be extended six inches into the lower course , a small quantity of mortar shall be put into the t hole , the ...
Contenido
66 | |
74 | |
80 | |
86 | |
88 | |
102 | |
108 | |
116 | |
123 | |
124 | |
126 | |
129 | |
131 | |
132 | |
133 | |
134 | |
135 | |
157 | |
158 | |
164 | |
170 | |
172 | |
176 | |
178 | |
183 | |
185 | |
186 | |
190 | |
195 | |
198 | |
215 | |
216 | |
225 | |
348 | |
Otras ediciones - Ver todas
Engineering Contracts and Specifications; Including a Brief Synopsis of the ... J. B. 1850-1902 Johnson Sin vista previa disponible - 2015 |
Términos y frases comunes
accepted agreement allowed amount approved asphalt bars beds bidder bolts bond breach brick broken stone cast iron castings cement mortar cent clause clean complete concrete construction contract contractor cost course Croton dam cubic yard damages defects depth diameter dimension stone dimensions discharge elastic limit embankments engineer estimates excavation exceed face stones Fahrenheit feet filled finished following specifications furnished further agrees grade gravel headers holes inches in thickness inches thick joints kind laid less liquidated damages manner Mary's Falls Canal material measure ment mixed necessary paid party pavement paving payment performance piece pipe and specials pipe or special plans Portland cement pounds per square proper proposals pump rammed rejected riprap rivets rock sand seal sewer square inch steel stone masonry strength surface tensile tensile strength thereof tion valves walls water commissioner wearing course width wrought iron
Pasajes populares
Página 58 - Where two parties have made a contract which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either arising naturally, ie, according to the usual course of things, from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties, at the time they made the contract, as the probable result...
Página 59 - ... such as may fairly and reasonably be considered either arising naturally, ie according to the usual course of things from such breach of contract itself, or such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract, as the probable result of the breach of it.
Página 44 - Sterling or upwards, shall be ' allowed to be good, except the Buyer shall accept Part of the ' Goods so sold, and actually receive the same, or give something ' in earnest to bind the Bargain, or in part...
Página 30 - A valuable consideration in the sense of the law may consist either in some right, interest, profit, or benefit accruing to the one party, or some forbearance, detriment, loss, or responsibility given, suffered, or undertaken by the other.
Página 84 - Payment well and truly to be made, we bind ourselves, and each of us, our, and each of our Heirs, Executors and Administrators jointly and severally, firmly by these Presents.
Página 299 - In testimony whereof, the said parties of the first part have hereunto set their hands and seals the day and year first above written.
Página 43 - ... or upon any contract or sale of lands, tenements, or hereditaments, or any interest in or concerning them; or upon any agreement that is not to be performed within the space of one year from the making thereof; unless the agreement upon which such action shall be brought, or some memorandum or note thereof shall be in writing, and signed by the party to be charged therewith, or some other person thereunto by him lawfully authorized.
Página 18 - It is furthermore hereby provided and mutually agreed, that no suit or action against this company, for the recovery of any claim by virtue of this policy, shall be sustainable in any Court of Law or Chancery until after an award shall have been obtained fixing the amount of such claim in the manner above provided...
Página 5 - If there is any truth to the old proverb that "[o]ne who is his own lawyer has a fool for a client," the Court by its opinion today now bestows a constitutional right on one to make a fool of himself.
Página 272 - ... and he shall determine all questions in relation to said work and the construction thereof, and he shall in all cases decide every question which may arise relative to the execution of this contract on the part of the contractor, and his estimate and decision shall be final and conclusive upon snld contractor; and such estimate and decision.